March Update: Cadent
Only four months after steelwork began, the new Cadent HQ is making great progress, courtesy of McLaren Construction Group.
Over the last month, McLaren has started the internal works as the general office structure progresses along with the multi storey car park.
Their next focus is continuing the installation of the office curtain wall system,, main and plant room roof ongoing, the completion of the office ground floor concrete slab, completion of the steelwork for the multi storey car park and continuing the work on the upper floor slabs.
The Prospero Anty Park team are very excited to see this new high spec office coming together.
For more information on the Park and how it can work for you, click here.